PET Blower Air Pressure Drops: Compare Demand and Delivery

A compressor display can look stable while pressure at the blower falls during demand peaks. Compare synchronized measurements at defined locations and reference conditions. High-pressure blowing air and low-pressure control air must remain separate in the investigation.

Follow the observed pattern

What you observe What to compare next
Compressor pressure is stable, blower pressure falls Compare synchronized supply and machine-inlet trends, dryer and filter conditions, and network configuration. Pressure loss under flow requires a different review from a static reading.
Several users peak together Align blower demand, other consumers, compressor loading and receiver behavior. Ask the air-system designer to assess simultaneous demand using the required reference-air basis.
Only startup or recovery is affected Record the sequence after a stop and the actual air-system readiness signals. Check the agreed operating envelope with the OEM before changing limits or adding storage.

Evidence to send with a support request

Send pressure trends with units and gauge or absolute basis, instrument positions, demand timing, air-system schematic and recent maintenance. Reference-air volume and compressed pipe volume are not interchangeable; preserve air-quality requirements during capacity review.

Illustrative diagnostic comparison

If supply and inlet pressures are read at different times, their difference cannot establish network loss. A synchronized event that repeats at the blower inlet is stronger evidence. Receiver sizing or a compressor upgrade still requires a system-specific design review.

Confirm the next action

Record the bottle, cap and material lot; machine and format recipe; time, speed and operating state. Separate direct observations from suspected causes. Preserve an unchanged comparison and identify who approved any trial.

  1. Record the approved change, comparable before-and-after observations, defect counts with their denominators, and quality or maintenance approval. A symptom disappearing once does not establish a durable correction.
  2. Repeat the check during the operating state that originally produced the defect. Keep restart losses and rejected product in the record; a faster machine reading alone is not proof of improvement.

Use approved site procedures and the machine manual. Isolate energy before physical inspection or clearing a jam; never bypass guards or interlocks. Quality personnel decide containment and release of affected product. These guides do not prescribe universal pressure, temperature, torque or cleaning settings.

Download the investigation record CSV

Required evidence — High- and Low-Pressure Air Network for PET Blowing

Input or result / Unit Evidence to request Substitution to avoid
Reference air per bottle (L (reference conditions)) Ask for per-bottle air use with the bottle format, operating case and declared reference pressure and temperature. Retain the measurement or supplier test basis. Reference litres and compressed operating volume are not interchangeable. A consumption number without its reference conditions cannot be matched reliably to a compressor supply figure.
Bottle rate (Bottles/h) Identify the counted bottle boundary and the exact observation interval. Retain opening and closing counter readings, accepted quantity and operating mode so the hourly rate can be reproduced. A machine nameplate rate, instantaneous display and accepted output over a shift are different records. Do not substitute one for another without stating the change of basis.